SEA requests new environmental documentation for Section 3 of Metro Line 9.

calendar_today
Share
SEA requests new environmental documentation for Section 3 of Metro Line 9.

Santiago Metro will have until October 7, 2026, to respond to the third ICSARA corresponding to the underground extension that will connect La Pintana with Plaza de Puente Alto.

 

The Environmental Assessment Service of the Metropolitan Region submitted to Santiago Metro the third Consolidated Report of Clarifications, Rectifications, and Additions Request (ICSARA), corresponding to the Environmental Impact Study for Section 3 of the future Line 9.

The state-owned company must submit its response, via a new addendum, by October 7, 2026, continuing the environmental assessment process for this important underground infrastructure project.

The assessed section involves an estimated investment of US$786.9 million and covers an approximate extension of 8.31 kilometers, entirely underground. The route will begin in La Pintana, proceed south along Santa Rosa Avenue, and then continue along Sargento Menadier Avenue and Balmaceda Avenue, until connecting with the current Line 4 at Plaza de Puente Alto station.

Five Stations and Six Construction Shafts

 

The project includes the construction of five stations, six shafts, which will later function as forced ventilation facilities, and a maneuvering tail track in the Puente Alto commune. The projected average distance between stations will be approximately two kilometers.

The section will utilize part of the underground infrastructure located between the future Gabriela station, in Plaza de La Pintana, and the Line 9 workshops and depots. This section was environmentally approved in May 2025 as part of the project’s initial works.

The extension to Puente Alto will allow the network to incorporate areas such as Bajos de Mena, strengthening connectivity in the southern sector of Santiago and facilitating access to high-capacity public transport for communities that have historically faced greater mobility challenges.

A Completely Underground Line

 

In its full configuration, Line 9 will feature 19 stations and approximately 27 kilometers of extension, connecting Recoleta with Puente Alto along the Santa Rosa Avenue axis. Its construction and commissioning will be carried out in stages.

According to the reported planning, the section between Bío Bío and La Pintana would become operational in 2030; the extension to Puente Cal y Canto is projected for 2032, while the connection between La Pintana and Plaza de Puente Alto is expected for 2033.

The issuance of this third ICSARA does not yet constitute environmental approval for Section 3. It is a stage in the procedure through which the authority requests additional or more precise technical and environmental documentation necessary to continue with the project’s evaluation.

Sources: , official project file at SEA, and Presidency of the Republic.

smart_toy

Exclusive Feature

Available only for CTES Members

The AI Agent is an advanced tool that allows you to perform smart searches, analyse technical documents, and instantly resolve questions about underground works.

search
Smart semantic searches
menu_book
Analysis of over 5,000 documents